View Full Version : Question about resources



dbigby
11-30-2010, 10:20 PM
I am trying to make a master project that encapsulates three other subprojects together. The subprojects already have resources allocated to them, there linked, and times are perfect, the have cost assoicated with the resources. but I tried using the merge button, the main problem became the fact all three resources have a lot of same kind of tools, Like all three of projects use a hammer, I just want to know what I should do so I can just have 1 resource sheet, and the times get all jacked up when I merge them.

Chabu
04-24-2011, 05:03 AM
It looks like you want to use a shared resource pool.
Open you three projects, open a new blank project (save it witha name like "resource pool" doesn't matter really)
In your projects go to tools/shared resources (not 100%, I don't have project here at home) and select your new pool. (do this for every one of your projects.
Msproject should merge you resources together (if the name is the same)

GROOKNET
03-31-2012, 07:33 AM
Thank you