marcoperry
11-30-2018, 03:13 AM
I have to analyze the relations of the FS type between activities, in order to eliminate the redundant relationships.

23302
In the example shown, the FS relation between task 1 and 4 is useless and redundant.

In a Gantt with many activities it is difficult to identify these relationships.

I would like to develop a sub-vba to identify these possible redundancies but I have not succeeded.Marco