    Is there a way to like reverse engineer code in VBA? I want to write a series of numbers in a double skew shape. An example is below:
    0 0.857143 1.714286 1.392857 1.071429 1.392857 1.714286 0.857143 0

    If you put these into an excel document you will find that they add to 9. I am writing a program that has a time period in number of months and an amount of work to be done also in an amount of months. So for this example, there are 9 months with 9 months of work to be done throughout those nine months. I have already accomplished evenly distributing, rising, falling, a normal distribution curve and an early and late skew curve. This curve would look like if you combined the early and late skew curves. The problem I am having is finding a point in the data where it rises and falls correctly. Here's an example of the math behind Early Skew written in code:

    Case 4  ' Early Skew Distribution
            
            sSkewSlope1 = CalculateSkewSlope1(lSubPeriods, sTotalEffort)
            sSkewSlope2 = CalculateSkewSlope2(lSubPeriods, sTotalEffort)
            
            sQuarterSubPeriods = Int(lSubPeriods / 4)
           
            For sIndex = 1 To lSubPeriods - 1
            
                If sIndex < sQuarterSubPeriods Then sMonthlyEfforts(sIndex) = sIndex * sSkewSlope1                                    'Calls on steep slope data for data below 1/4 of the total monthly effort
                If sIndex >= sQuarterSubPeriods Then sMonthlyEfforts(sIndex) = ((lSubPeriods - 1) - sIndex) * sSkewSlope2             'Calls on gentle slope data for data above 1/4 of the total monthly effort
                
            Next sIndex
    Which calls on:

    Public Function CalculateSkewSlope1(lSubPeriods As Long, sTotalEffort As Single) As Single
    
    Dim sIndex1 As Long, sIndex2 As Long, sArea As Single, sTotal1 As Long, sTotal2 As Long
    
    sArea = sTotalEffort / 4
        
    sTotal1 = 0
    sTotal2 = 0
    
    For sIndex1 = 1 To Int(lSubPeriods / 4)
    
        sTotal1 = sTotal1 + sIndex1
        
    Next sIndex1
    
    For sIndex2 = 1 To (Int(lSubPeriods / 4) - 1)
    
        sTotal2 = sTotal2 + sIndex2
        
    Next sIndex2
    
    
    If (lSubPeriods / 4) = Int(lSubPeriods / 4) Then CalculateSkewSlope1 = sArea / sTotal2
    
    If (lSubPeriods / 4) <> Int(lSubPeriods / 4) Then CalculateSkewSlope1 = sArea / sTotal1
    
    End Function
    
    
    Public Function CalculateSkewSlope2(lSubPeriods As Long, sTotalEffort As Single) As Single
    
    Dim sIndex As Long, sArea As Single, sTotal As Single
    
    sArea = (sTotalEffort * 3) / 4
    
    sTotal = 0
    
    For sIndex = 1 To (((lSubPeriods - (lSubPeriods / 4))) - 1)
    
            sTotal = sTotal + sIndex
    
    Next sIndex
        
    CalculateSkewSlope2 = sArea / sTotal
    
    
    End Function

    Any suggestions?
    Last edited by Bob Phillips; 07-02-2014 at 12:51 PM.

  2. #2
    Distinguished Lord of VBAX VBAX Grand Master Bob Phillips's Avatar
    Joined
    Apr 2005
    Posts
    25,453
    Location
    Yeah, use code tags and post Excel questions in the Excel forum.
    ____________________________________________
    Nihil simul inventum est et perfectum

    Abusus non tollit usum

    Last night I dreamed of a small consolation enjoyed only by the blind: Nobody knows the trouble I've not seen!
    James Thurber

Tags for this Thread

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •