How to calculate the daily number of people
Hi! Dear gurus. Thank you in advance for your attention to my question. I really hope to help. On the agenda the schedule/plan of construction works. The challenge is this: how can I get MS Project through the total daily number of people on the site in the form of a diagram, report, or anything else. For example is digging a ditch 5 people from 1.03.15 to 7.03.15, and the removal of soil making 4 people from 7.03.15 to 9.03.15. Therefore from 1.03 to 6.03 on the object working 5 persons, 7.03 - 9 persons,8.03-9.03 - 4persons.I tried with many ways, but nothing.