MS Project 2013 2016
I have to analyze the relations of the FS type between activities, in order to eliminate the redundant relationships.
Cattura3.jpg
In the example shown, the FS relation between task 1 and 4 is useless and redundant.
In a Gantt with many activities it is difficult to identify these relationships.
I would like to develop a sub-vba to identify these possible redundancies but I have not succeeded.Marco