Create Column for Each Resource
I have a requirement to export an MS Project file to Excel for import to another application.
The request is to have a unique column for each resource required in the project by Task.
So a line of data for a task would include:
Task Name - Work Estimate - Resource A Work Estimate - Resource B Work Estimate .....
Build A 20 hrs 10 hrs 10 hrs
Creating the column as a Text Column is easy. Customizing that column to include the work demand of a specific resource is where I am struggling.
Thanks in advance.
I am happy to provide the data in a different format if it helps explain my request.