Greetings,
I have created a macro to update my reporting filters using the current date. This is a code snippet:
My problem is that the Active test is not working. When I run the macro and apply the filter, I receive all tasks meeting the date criteria on all tasks, inactive tasks included. Am I applying to wrong code test or type for Active?' Set the filter to tasks that should have finished by now FilterEdit Name:="_Tasks Not Finished", _ TaskFilter:=True, Create:=True, OverwriteExisting:=True, _ FieldName:="Finish", Test:="is less than or equal to", Value:=Now(), _ FieldName:="% Complete", Test:="does not equal", Value:=100, _ FieldName:="Active", Test:="equals", Value:="Yes", _ ShowInMenu:=True
I have searched Bing, Google, and every MS Project thread on this site but found no solution.
Thank you.



Reply With Quote